Provide temporary shoring at the fifth and sixth floor levels to support existing wood joists framing at the existing fire damaged roof assembly to ensure structural stability.
Garage repairs: REPAIRS TO DELAMINATEDCONCRETE SLAB TOPSIDE, UNDERSIDE, BRICK MASONRY WALLS AND RESUPPORTOF EXISTING SLABS FROM EXISTING STEEL FRAMING, WATERPROOFING REPAIRS, ROUTI…
Exterior facade masonry repairs, replacement of damaged brick, window sills, window lintels and replacement of select masonry roof parapets.
Filing for installation of refrigeration equipment complete with condensers, evaporators and piping. install water heater flue pipe and combustion air duct from cellar mechanical r…
Party wall-tie back and water proofing / parging at exposure 4, in-conjunction with immediate emergency declaration (ied) full demo of adjacent lot
work includes repair of north facing exterior wall and fire damage to the roof. NO CHANGE IN USE OR OCCUPANCY
Installation of solar system on the roof as per plan. No change in use, egress or occupancy
Rooftop solar installation. no change to use, occupancy or egress.
installation of solar panels, rooftop, railed, grid-tied, 7 modules, 2.87 kw
Structural repair to existing house as follows: first floor rear kitchen area - floor & ceiling joists (separation area) & roof above. second floor - sister floor joists throughout…
Proposed interior and exterior renovation on cellar, 1st floor thru 5th floor, and roof as per plan. convert to two-family. obtain new certificate of occupancy.
Structural plans for enlarged fourth floor, propose new roof, steel stairs and change flooring of all levels from wood joists to light gauge steel.
Solar installation on E house roof in conjunction with Alt-Co application Q01129003-I1
Installation of temporary adjacent roof protections per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this a…
General construction to take place on the 11th floor Roof as per plans filed herewith. No change in use, egress, or occupancy.
Filing herewith tax abatement application for installation of roof-mounted solar panels. no change in use, egress, or occupancy.
Roof and Facade repair project. No change in use, egress or occupancy.
Application filed for facade and roof repair as per plan. No change in use, egress and occupancy
Facade repairs including limestone repairs and replacement, brick replacement, window sill replacement, cut and pointing at missing or deteriorated mortar joints, limestone sill re…
Facade and roof repairs. no change in use, egress, or occupancy.