Building Permits in ZIP 10021
Manhattan, NY — 781 permits filed recently
781 permits
Herewith filing underpinning work, as per plans submitted. Filed in conjunction with ALT 1#: 121330327 and SOE#: M00852650.
Herewith filing partial demolition work/sequence, as per plans submitted. Work is filed in conjunction with ALT 1 #: 121330327 and M08008884.
Installation of hvac equipment, ductwork, and piping for apartment renovation. no change in use, egress or occupancy.
Herewith filing support of excavation to provide foundation bench, as per plans submitted.
INSTALLATION OF NEW MECHANICAL SYSTEMS IN ASSOCIATION WITH TOWNHOUSE RENOVATION, INSTALL NEW VRF HEAT PUMPS AND ASSOCIATED PIPING AND DUCTWORK. INSTALL NEW ERVVENTILATION SYSTEM. No change to use, egr...
Herewith filing partial demolition work/sequence, as per plans submitted. Work is filed in conjunction with ALT 1 #: 121330327 and M08008884.
Installation of a temporary enclosure system per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Renovate existing building including new egress stair and new elevator. No change in use and no change to bulk of the building.
Herewith filing underpinning work, as per plans submitted. Filed in conjunction with ALT 1#: 121330327 and SOE#: M00852650.
Mechanical work associated with townhouse renovation as per plans filed herewith.
Interior demolition as per plans filed. no change to use egress nor occupancy.
Installation of a 5 ton, water cooled, Climatemaster A/C unit with a single line supply air duct layout, ceiling return air grilles, and condenser water supply & return piping and condensate drain on...
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Support of excavation scope as related to townhouse renovation as per plans filed herewith.
Installation of hvac equipment, ductwork, and piping for apartment renovation. no change in use, egress or occupancy.
Herewith filing support of excavation to provide foundation bench, as per plans submitted.
Structural demolition as per plans filed herewith.
Interior renovation of apartment 11-j on 11th floor as indicated on plans filed herewith. no change of use egress or occupancy.
Temporary shoring and bracing at rear wall at each floor level
Minor partition work for construction of new closets for existing bedrooms and new finishes within existing master bathroom and guest bathroom. plumbing work filed under subsequent application.