Interior renovation of the 27th Floor (Cliffwater), including interior partitions, doors, ceilings and finishes, as per plans. No change to use, egress, or occupancy.
Level 23 installation of new ducted hvac systemconnected to existing building air handling units,installed in coordination with architectural layout.existing perimeter induction un…
Level 23 general construction for office fitoutincluding new partitions, interior glazing, flooring,ceiling, lighting, and lighting controls.no impact on present zoning of building…
Modifications to the existing HVAC system and associated ducts and piping and installation of new units on the 27th Floor (Cliffwater), as per plans. No change to use, egress, or o…
Removal and construction of interior partitions, doors and ceiling as shown on drawings. No change in use, egress or occupancy.
Structural Modifications on the 45-46th Floor as per plans (Willkie Farr Gallagher - Phase 1.) No change to use, egress or occupancy.
Structural Modifications on the 36-37, 43-44th Floors as per plans (Willkie Farr Gallagher - Phase 1.) No change to use, egress or occupancy.
Modifications to the existing HVAC System and redistribution of ductwork and associated accessories on the 45th Floor as per plans (Willkie Farr & Gallagher - Phase 1.) No change t…
Structural Modifications on the 36th Floor as per plans (Willkie Farr Gallagher - Phase 1.) No change to use, egress or occupancy.
Miscellaneous Demolition and replacement of existing fireproofing. Installation of new partitions, doors, finishes and suspended ceilings on the 37, 43-44th Floor as per plans (WFG…
Modifications to the existing HVAC System and redistribution of ductwork and associated accessories on the 34 and 35th Floors as per plans (Willkie Farr & Gallagher - Phase 1.) No…
Modifications to the existing HVAC System and redistribution of ductwork and associated accessories on the 36th Floor as per plans (Willkie Farr & Gallagher - Phase 1.) No change t…
Structural Modifications and installation of stairs on the 34-36th Floors as per plans (Willkie Farr Gallagher - Phase 1.) No change to use, egress or occupancy.
Installation of protective wire fence and bollards for exterior sprinkler system RPZ.
Install ductwork and supplemental packaged ac unit (water cooled).
Remove and construct interior partitions, ceilings & doors.
Structural modifications as per plans filed herewith. no change to use egress or occupancy.
Minor demolition with installation of new partitions, doors, ceilings and finishes on the 6th floor as per plans. No change to use, egress or occupancy.
Mechanical modifications as per plans filed herewith. no change to use egress or occupancy.
General construction as per plans filed herewith. no change to use egress or occupancy.