fairview riverside. 10 floor locker room upgrade
Installing 2 VAVs from existing main duct with reheats and modifying exhaust ducts for shower/change room M1003-1 and shower/change room 1003 BLDG11696 Work is located on level10…
Floor 10 Upgraded Locker Room
Addition of (x11) Overflow Roof Drains and a corresponding Secondary Storm Drainage System within the Allina TAF Facility
Piping in reheat coil valves for new reheat coils associated with other mechanical work listed under permit BLDG115535 BLDG1155235 . BLDG1155319
BLDG1155235 2 floor area A and B. Reconfigure piping, low pressure ducts systems and VAV's with hot water coils. Also adding Fire/Smoke damper to existing return main at grid S1.