Erect 69 Story new building. Required parking located on adjacent zoning lot.
HUB Consultation on 4/22 (under 200 East 75th Street Address). Please assign to HUB examiner. New 18-story building.
Structural modifications: relocation of columns in cellar to allow clearance for new equipment, new foundations & framing at all floors for new elevator, new entry vestibule, colum…
Renovations to hask-mission house including installation of commercial cooking and ventilation in 1st floor kitchen. interior partitions and ceilings as per plans.
Filing to remove and install new mechanical systems as per plans filed. no change to use, egress or occupancy.
Proposed interior non-structural alteration of cellar & 1st floor. the scope is limited to the interior renovation of non-load walls, floors, and cieling. no change to use, egress…
Partial demolition of floor slab with bracing for convenience stair build-out as per plans filed. no change to use, egress or occupancy.
Emergency work order (control #350415): emergency removal of temporary structure. platform and courts framing to remain as per plans.