Revision to Permit No. B2601297 Replacement of continuous foundation wall and footing with isolated concrete piers and spread footings Installation of structural wood posts supported on concrete pedestals/piers Excavation limited to individual footing locations only; no continuous trenching Updated structural details and coordination per structural drawings There is no change to building footprint, height, massing, or overall layout. This revision is limited to the foundation system modification only. All other previously approved work remains unchanged. Tree protection measures and erosion and sediment control requirements have been implemented on site in accordance with DOEE inspector direction and project arborist recommendations. Pre-construction meeting has been completed and approved. Affected work area: 256 sq.ft