168,000+ permits across 13 states. Drill down by trade, ZIP, or flag only the ones without a contractor on file.
Associated foundation work for new steel framed rear addition, new steel framed elevator shaft.
Sprinkler/Standpipe work for tenant Metropolitan Capital Partners on 9th floor.
Installation of sidewalk shed as per plans. no change in use, egress or occupancy.
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this applicat…
Installation of temporary sidewalk shed for pedestrian safety during construction. sidewalk shed shall comply with choater 33 of the nyc bc. no change in use, egress, or occupancy.
Unlimited owner reveals + same-day permits
Pro lifts the 10/month cap, drops the 7-day freshness delay, and lets you export any search to CSV. $79/mo for the first 100 subscribers.
Plumbing work for tenant Metropolitan Capital Partners on 9th floor.
Filing herewith for the plumbing work to be done
Demolition of sprinkler/standpipe system as shown.
New Building Construction of 16 story Medical Office Building
Demolition of sprinkler/standpipe system as shown.
Installation of temporary sidewalk shed as per plan. no change in use, egress or occupancy. the sidewalk shed along the front of the building and the backyard of the building and c…
Installation of temporary sidewalk shed as per plan. no change in use, egress or occupancy. the sidewalk shed is at building face at west 142nd street elevation
Filing to reconstruct retaining walls at west 186th street basketball court
test
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this applicat…
Installation of temporary sidewalk shed as per plan. no change in use, egress or occupancy. the sidewalk shed is at the west 143rd street elevation, the back of the building, and o…
Installation of temporary sidewalk shed as per plan. no change in use, egress or occupancy. the sidewalk shed is at the west elevation in front of the building adam clayton powell…
Installation of temporary sidewalk shed as per plan. there is no change in use, egress or occupancy. the sidewalk shed is at adam clayton powell blvd in front of the building.
Installation of temporary heavy duty sidewalk shed and supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or…
Temporary pipe scaffold as per drawings. scaffold shall comply with ch #33 of the nyc bc. no change in use, occupancy or egress under this application.