Remove/install new non-load bearing partitions and finishes. no change to occupancy, use or egress
Minor demolition with installation of new partitions, doors, suspended ceilings and finishes and sidewalk repair on the Cellar & 1st floors (Harry Winston -Fitout) as per plans. No change to use, egre...
Installation of temporary shoring and misc. concrete repairs as per plans submitted herewith. there is no change in use, egress or occupancy.
Installation of temporary privacy protective panel per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
general construction associated with ADA restroom on 2nd floor as per plans filed herewith. no changes in use, egress or occupancy.
Repair/replace deteriorated wood girders in cellar: remove 2 damaged beams, install W8x28 steel beams with Simpson A34 connectors, drilled/grouted anchors, temporary shoring, and local masonry repairs...
Modifications to the existing HVAC system on the Cellar floor (Harry Winston - Cellar Fitout) as per plans. No change to use, egress or occupancy.
Installation of temporary heavy duty sidewalk shed as per plans. no change in use, egress or occupancy. sidewalk shed shall comply with chapter #33 of 2022 the nyc building code. live load 300psf.
Repair/replace deteriorated wood girders in cellar: remove 2 damaged beams, install W8x28 steel beams with Simpson A34 connectors, drilled/grouted anchors, temporary shoring, and local masonry repairs...
Modifications to the existing HVAC system on the Cellar floor (Harry Winston - Cellar Fitout) as per plans. No change to use, egress or occupancy.
Installation of temporary heavy duty sidewalk shed as per plans. no change in use, egress or occupancy. sidewalk shed shall comply with chapter #33 of 2022 the nyc building code. live load 300psf.
Repair/replace deteriorated wood girders in cellar: remove 2 damaged beams, install W8x28 steel beams with Simpson A34 connectors, drilled/grouted anchors, temporary shoring, and local masonry repairs...
general construction associated with ADA restroom on 2nd floor as per plans filed herewith. no changes in use, egress or occupancy.
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Filing for renovation of apartment Apt: 2901; no change to use, egress or occupancy.