Building Permits in ZIP 10014
Manhattan, NY — 1,093 permits filed recently
1,093 permits
Modification to existing plumbing system in apt. #11N as per plans filed herewith. No change in use, egress or occupancy.
Installation of new sidewalk shed for hs 560m at 16 clarkson street, manhattan as indicated on plans. there will be no change in the use, egress, or occupancy under this application.
Installation of pipe scaffold for hs 560m at 16 clarkson street, manhattan as indicated on plans. there will be no change in the use, egress, or occupancy under this application.
Install plumbing fixtures in conjunction with construction job m01340195.
Interior renovation of exist. 1st commercial space on 1st floor. no change to exist. use, egress & occupancy.
VERIZON - Relocate/replace 6 antennas & 6 RRHs, relocate 3 MDBs, install 1 RRHs, remove 3 ballast frames, remove 4 cabinets from existing platform and install 1 new cabinet. All work on the roof.
Installing and removal of plumbing fixtures as per plans. no change to use egress or occupancy
Suspended Scaffold for Facade Restoration as shown on plans
General construction modifications taking place on the 2nd floor as per plans filed herewith. No change in use, egress or occupancy
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Suspended Scaffold for Facade Restoration as shown on plans
Removal & installation of duffusers & associated ductwork, piping & accessories. instllation of fan coil units. all exisitng mechanical equipment, ductwork, piping & accessories to be removed as per p...
Installation of heavy duty side walk shed.as per plan.
To resolve ecb violation #39529235h, #39526338r, #39526339z by removing illegal construction fence. no change of use, egress or certificate of occupancy.
Mechanical modificiations and installations for apartment renovation as per plans filed.
Reconfigure existing ductwork runs and install 2 new diffusers. re-locate thermostats.
Standpipe modifications taking place on the 2nd floor as per plans filed herewith. No change in use, egress or occupancy
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Structural work for reinforcement of existing floof framing, and repairs of the deteriorated walls as per plans filed herewith.
Engineered enclosure system for roof and overhead protection of adjoining equipment and spaces