Varsity Plbg And Htg Inc
Permits (106)
Replace sump pump and provide new drains with associated piping, remove/reinstall water closet, replace cold water piping/south water service, replace storm piping, provide new RPZ for water service,...
Remove and replace 7 roof drains and associated piping. Extend 9 roof vents. Remove and replace 3 catch basins.
Replace sump pump and provide new drains with associated piping, remove/reinstall water closet, replace cold water piping/south water service, replace storm piping, provide new RPZ for water service,...
Q074_Remove and replace existing CW, HW, and HWR piping and insulation in tunnel. Install backwater valve assembly, sump pumps. Disinfect water piping, roto-rooter and pressure clean existing yard dra...
Q074-replace roof drains with new. extend vent stacks. replace area drains & trench drains.
Q074-replace roof drains with new. extend vent stacks. replace area drains & trench drains.
Q074_Remove and replace existing CW, HW, and HWR piping and insulation in tunnel. Install backwater valve assembly, sump pumps. Disinfect water piping, roto-rooter and pressure clean existing yard dra...
Replac exist (7) roof drains. relocate exist (4) vent stack & extend 4' above finished roof. Power flush, clean & test new vent stack. Power flush & clean entire storm drains system, all leaders & sto...
Remove existing roof drains and provide new roof drains.
Replacing existing area drains with area drains equipped with ADA Compliant Grates and approximately 2 LF of CIP.
Remove existing roof drains and provide new roof drains.
Replacing existing area drains with area drains equipped with ADA Compliant Grates and approximately 2 LF of CIP.
Replac exist (7) roof drains. relocate exist (4) vent stack & extend 4' above finished roof. Power flush, clean & test new vent stack. Power flush & clean entire storm drains system, all leaders & sto...
New Storm-water sewer work from the existing detention tank that is routed through the site. Work includes replacing the storm sewer connection to the city sewer in Autumn Avenue and associated sitewo...
New Storm-water sewer work from the existing detention tank that is routed through the site. Work includes replacing the storm sewer connection to the city sewer in Autumn Avenue and associated sitewo...
New Storm-water sewer work from the existing detention tank that is routed through the site. Work includes replacing the storm sewer connection to the city sewer in Autumn Avenue and associated sitewo...
Replace and relocate 8-5 roof drains.
Replace and relocate 8-5 roof drains.
P.S. 252-K: SUBSEQUENT FILING OF PLUMBING WORK TYPE. Areaway drainage replacement; installation of foundation drains and sump pump.