3,509 issued permits in Midtown-Times Square, part of Manhattan, New York. Refreshed every 6 hours from the city's public permit feed.
3,509 permits
Application filed for modification to mechanical systems and related duct work as per plan. there is no change to use, egress, or occupancy filed under this application.
Remove 52 sprinkler heads. install 9 new temporary sprinkler loop heads and piping. install 51 new permanent sprinkler heads and piping.
Provide mechanical work for the 18th fl of an existing office building, work include installing ac indoor units, duct work and ventilation system. no change in use, egress, or occu…
Filing herewith phased structural construction of 343M to include one-story structure on north side of site and associated below grade basements and foundations
Installation of a suspended scaffold for Facade Inspection and repair as per plan submitted. No change to egress or occupancy.
Removal and installation of interior non-bearing partitions and related finishes as per plans filed herewith. No change in use, egress or occupancy.
Amendment cd5: fisp repairs per plans . no change in use, egress or occupancy. adding new drops and work cage location options
Extend existing advertising wall sign 8280 SF according to plan. Structure filed under separate application No. M01343634. Approved by Department of City Planning -C250118 ZSM and…
Installation of temporary betamax hoist as per plans. no change in use, egress or occupancy.
Herewith Filing Modifications to Existing Mechanical Systems in conjunction with interior renovations of existing offices as per plans.
Mechanical: Modifications to the existing HVAC system on the (23rd Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
Installation of temporary needle beams as per plans. needle beams shall comply with chapter #33 of the 2022 code. no change in use, egress or occupancy under this application.
Modification/addition to existing HVAC and associated ductwork/piping as shown on drawings. No change in use, egress or occupancy.
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with thi…
Interior demo & reno of non-load bearing partitions, walls, doors, ceiling & finishes as indicated on plans,
Facade Inspections
Job filed minor plumbing fixture removal and replace within existing rough-in on 18th flooras per plan. no change of use, egress or occupancy under this application.
Extend advertising wall sign structure according to plan. Sign filed under app# M01343632. Approved by Department of City Planning -C250118 ZSM and N250189 ZRM No change of use, eg…
New opening in existing interior masonry wall, lintel and jamb reinforcing as shown on drawings. no change to use, egress or occupancy.