Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the (23rd Floor-Orrick-Buildout) as per plans. No change to use, egress or occupancy…
Filing herewith for Plumbing modifications as per plans. Removal and Installations of plumbing fixtures and associated piping. No change to use, egress or occupancy.
Amendment CD5
Sprinkler work as per drawings. no change touse, egress or occupancy.
Installation of a suspended scaffold for Facade Inspection and repair as per plan submitted. No change to egress or occupancy.
Modification/addition to existing HVAC and associated ductwork/piping as shown on drawings. No change in use, egress or occupancy.
Interior demo & reno of non-load bearing partitions, walls, doors, ceiling & finishes as indicated on plans,
Amendment cd5: fisp repairs per plans . no change in use, egress or occupancy. adding new drops and work cage location options
Mechanical exhaust system for the existing kitchen on a second floor. No change of use, egress or occupancy.
Installation of a temporarily heavy-duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with thi…
Herewith filing interior renovations to office space as outlined in plans submitted. No change in use, egress or occupancy is proposed under this application.
Installation of temporary needle beams as per plans. needle beams shall comply with chapter #33 of the 2022 code. no change in use, egress or occupancy under this application.
Extend existing advertising wall sign 8280 SF according to plan. Structure filed under separate application No. M01343634. Approved by Department of City Planning -C250118 ZSM and…
Facade Inspections
Job filed minor plumbing fixture removal and replace within existing rough-in on 18th flooras per plan. no change of use, egress or occupancy under this application.
Removal and installation of interior non-bearing partitions and related finishes as per plans filed herewith. No change in use, egress or occupancy.
Installation of temporary betamax hoist as per plans. no change in use, egress or occupancy.
Mechanical: Modifications to the existing HVAC system on the (23rd Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.