Turner Construction Compa
Permits (122)
Filing herewith civil scope for non-structural demolition aka removal scope of planters, benches, trees, etc. at garage roof - plaza level (Damrosch Park) as per plans. No change in use, occupancy, or...
Filing herewith structural partial demolition scope inside garage/parking structure and at the garage/parking structure roof/plaza level which includes a slab cut as per plans. No change in use, occup...
Filing herewith general construction for non-structural demolition aka removal scope of planters, benches, trees, etc. at garage roof - plaza level (Damrosch Park) as per plans. No change in use, occu...
Filing herewith civil scope for non-structural demolition aka removal scope of planters, benches, trees, etc. at garage roof - plaza level (Damrosch Park) as per plans. No change in use, occupancy, or...
General construction including renovations to 2nd floor Market Hall and terrace, as shown on plans filed herewith. No change in use, egress, or occupancy.
General construction including renovations to 2nd floor Market Hall and terrace, as shown on plans filed herewith. No change in use, egress, or occupancy.
Filing herewith installation of general contractor's temporary field office trailer with ramp and stairs per Article 111 - Temporary Structures and Uses - 28-111 at Jaffe Drive as per plans. No change...
Filing herewith installation of general contractor's temporary field office trailer with ramp and stairs per Article 111 - Temporary Structures and Uses - 28-111 at Jaffe Drive as per plans. No change...
Filing herewith interior demolition of existing mechanical/hvac systems at the garage/parking structure to make way for new theater building/structure as per plans. No change in use, occupancy, or egr...
Architectural modifications in support of upgrades to the building facade and interior finish. No change in use, egress or occupancy.
Filing herewith general construction/architectural scope inclusive of demolition of interior partitions/finishes, etc. inside the garage/parking structure and its roof as per plans. No change to use,...
Architectural modifications in support of upgrades to the building facade and interior finish. No change in use, egress or occupancy.
Filing herewith general construction/architectural scope inclusive of demolition of interior partitions/finishes, etc. inside the garage/parking structure and its roof as per plans. No change to use,...
Filing herewith for superstructure as per plans.
Filing herewith for superstructure as per plans.
Modifications to the existing mechanical system including installation of DOAS boxes and associated finishes. No change in use, egress or occupancy.
Modifications to the existing mechanical system including installation of DOAS boxes and associated finishes. No change in use, egress or occupancy.
Mechanical work for Liberty Mutual on 10th floor
Mechanical work for Liberty Mutual on 10th floor
Structural work on the 11th floor (Tai Ping Edward Fields showroom) as indicated on drawings.