2,817 issued permits in Midtown-Times Square, part of Manhattan, New York. Refreshed every 6 hours from the city's public permit feed.
2,817 permits
Filing for plumbing and sprinkler work associated with interior renovation of 17th & 18th floors thomson reuters office as per plans
Early-phase Mechanical modifications to fan powered boxes and fans on Floors 07 through 08. Construction costs and filing fees included in full-floor Mechanical job #M01293902-S1.…
Installation of suspended scaffold for facade work or inspection
Mechanical work as per plans filed. application filed in conjunction with new building 121208095.
AT&T - Installation of gas line from basement to roof routed along rear of building in existing conduit (10097550) as per plans. Installation of gas meter in the basement. No chang…
Structural Modifications associated with escalator demo/rebuild, slab infill and new stair opening, new footings, new partial deck on the Cellar & 1st Floor as per plans (Retail Sp…
Replacement of 2 ton split system in the 20th floor, conference room. no change to egress, use, or occupancy.
Structural Modifications: Infill with new lintels and install new lintels for louver openings on the 16th Floor as per plans (AHU Replacement. - Exterior Louver.) No change to use,…
Modification to existing mechanical system on the 8th floor as per drawings filed herewith. no change to use, occupancy, or egress
Modification of Cellar, 1st, Mezzanine, 3rd, 4th, 7th, 8th, 11th, 12th, 13th Mezzanine, 14th, 15th, roof per plans filed
Demolition and Construction of Partitions, Doors, Suspended Ceiling, Millwork, Wall & Floor Finishes and Renovation of Existing Pantry on Part of the 17th Floor. No Change to Occup…
Remove all mech equipment, and associated apparatus.
Installation of temporary sidewalk shed as per plans. no change in use, egress or occupancy.
Application file to amend existing certificate of occupancy #112741 for the cellar & 1st floor including a new mezzanine in conjunction with the 1st floor commercial space.
Temporary Enclosure System for Louver Work
Installation of temporary pipe scaffold as per plans. no change in use, egress or occupancy.
Modification/addition to existing HVAC and associated ductwork/piping as shown on drawings. No change in use, egress or occupancy.