1,780 issued permits in Upper East Side-Carnegie Hill, part of Manhattan, New York. Refreshed every 6 hours from the city's public permit feed.
1,780 permits
General construction scope of work: new non-structural partitions and millwork, new cabinetry, flooring, doors dropped ceilings and fnishes.no change to use occupancy or egress
Temporary Support of Excavation for proposed elevator pit.
Proposed installation of new plumbing fixtures as per plan, filed in conjunction with Alt-CO-NB # M01134636-I1.
Installation of a suspended scaffold for Facade Inspection and repair as per plan submitted. No change to egress or occupancy.
Plumbing work associated with interior renovation of Apartment 7B.
Installation of temporary sidewalk shed as per plans. no change in use, egress or occupancy.
Installation of temporary sidewalk shed for pedestrian safety during construction. sidewalk shed shall comply with choater 33 of the nyc bc. no change in use, egress, or occupancy.
Structural demo and shoring in conjuntion with alt-co m01134824-i1.
Installation of temporary sidewalk shed as per plan. no change in use, egress or occupancy.
Removal of existing roof membrane and installation of new roof membrane. Repair and restoration of existing stucco facade. No change in use, egress, or occupancy.
Installation of temporary wire mesh enclosure per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this applica…
Installation of mechanical and ventilation systems and associated ductwork.
Installation of temporary overhead protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this applica…
Installation of temporary material hoist per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
Installation of temporary pipe scaffold as per plans. no change in use, egress or occupancy.
Renovation of an existing apartment#9F of the ninth floor. Work includes non-structural demolition, general construction and modification of existing openings as per plans file her…
File suspended scaffold outrigger systems for facade restoration and inspection.
Mechanical work file in conjunction with the renovation of an existing apartment#9F of the ninth floor.
Installation of temporary sidewalk shed as per plan. there is no change in use, egress, or occupancy.. the sidewalk shed is in front of the building.