754 issued permits in Upper West Side-Lincoln Square, part of Manhattan, New York. Refreshed every 6 hours from the city's public permit feed.
754 permits
FISP INSPECTION (Facade Inspection Safety Program). INDUSTRIAL ROPE ACCESS TECHNIQUES AND METHODS. SEE ATTACHED PLANS. Designated Primary Site supervisor: Jesus Decola
Relocate plumbing fixture with new (1 wc, 1 lav, 1 sink); cap and remove (1 tub); install new plumbing fixtures at new roughing (1 dw, 1 w/m, 1 shower) at apt 9e on the 9th floor.
Facade repairs as per plans filed herewith. no change to use, egress or occupancy
Exterior facade restoration work and repairs as necessary and per plans submitted. No change in use, occupancy or egress proposed under this application.
Herewith file plumbing plans in conjunction with general construction for Apt. 25H.
Scope of work in unit 26t on 26th floor, removal and installation of non-loadbearing partitions as shown on plans. all plumbing work filed under separate application. no change to…
Hereby filing for the installation of plumbing fixtures and sprinkler heads for unit 19c. no change in use, egress or occupancy.
Application to repair brown stone/spotpointing on facade, windows caulking and paint also entire front power wash asper plan. no change in use, egress, and occupancy.
2nd floor interior renovation combining one dwelling unit and one store into a single residential unit. Work includes non-load-bearing partitions, mechanical, plumbing and electric…
installation of new mechanical piping, and all accessories related to the new gas fired hot water heaters. installation of new condensate pumps for existing heating system as per p…
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this appl…
Install (20) new sprinkler heads and relocate (17) existing sprinkler heads. no change in use, egress, or occupancy.
Proposed installation of heavy duty sidewalk shed as per plans. live load 300 lbs per square feet. sidewalk shed shall comply with chapter #33 of the nyc building code. no change i…
Work consists of new sanitary, domestic water, and sanitary vent piping to be installed throughout the existing tenant space.
Install plywood construction fence to protect the public during work under application #M01208213-I1
Remove and replace circular car turn around, walkways, planting beds, lobby entrance, lobby glass facade and canopy. no change in use, egress, or occupancy.
Herewith file to renovate eat-in & to-go store. work includes new plumbing fixture with associated piping, and fire-stopping is provided. modification of existing sprinkler head as…
Garage Repairs as per plans filed herewith. No change to use, egress, or occupancy.
The project scope of work includes the installation of vestibulee electric air curtain. There is no change in occupancy, scope, or egress