2,817 issued permits in Midtown-Times Square, part of Manhattan, New York. Refreshed every 6 hours from the city's public permit feed.
2,817 permits
Installation of temporary overhead protection & loading dock for hoist as per plans. temp. equipment shall comply with chapter #33 of the 2022 code. no change in use, egress or occ…
plumbing work in conjunction with the ot # M01348222-I1
Interior alteration to the 8th floor to include assembly space in conjunction with current business use occupancy. Filed in conjunction with PA M01334767-I1.
The project includes the installation of new steel beams to close existing floor openings at the second and third floors. A new non-load-bearing party wall separating building no.…
Installation of sidewalk shed as per plans. no change in use, egress or occupancy.
Sidewalk vault repairs. no change in use, egress or occupancy.
Install a ventilation system with make up air, etc. No change of use, egress or occupancy.
General construction work filed in conjunction with Alteration type 1 (no work) #: 123923068
Pl application filed herewith to perform plumbing roughing as indicated on drawings in conjunction with altco application m01340670, cap/remove existing plumbing piping and fixture…
Illuminated non-advertising double-face projecting accessory sign - kilwins. no change of use, egress or occupancy.
Installation of suspended scaffold for facade inspection/repair.
Demolition and general construction work on 16th floor as per plans. No change to use. egress or occupancy.
Removal of existing sprinkler head and installation of temp loop as per plans filed herewith. No change in use, egress or occupancy under this application .
Replacement of cracked brick masonry, repair of cracked terra cotta and stone units, replacement of deteriorated steel lintels. no change to use, egress, or occupancy.
Modification to existing Sprinkler system and plumbing fixtures as per plans filed herewith. No change in use, egress or occupancy under this application.
Installation of sidewalk shed to protect pedestrian from the facade repairs on the street facing facade.
Modification/addition to existing HVAC and associated ductwork/piping as shown on drawings. No change in use, egress or occupancy.
Minor demolition with installation of new partitions, doors, ceilings and finishes on the 18th floor (Derby Lane) as per plans. No change to use, egress or occupancy.
Modifications to the existing sprinkler system as per plans. No change to use, egress or occupancy.
Soe work in conjunction with elevator shafts and concrete foundations in the cellar and sub cellar of an existing structure