3,402 issued permits in Midtown-Times Square, part of Manhattan, New York. Refreshed every 6 hours from the city's public permit feed.
3,402 permits
Installation of temporary sidewalk shed as per plan. there is no change in use, egress, or occupancy.
Modifications to existing HVAC and ductwork as per plans filed herewith. No change to use, egress, or occupancy.
Removal of interior non-bearing partitions and related finishes as shown on plans. no chang to use, egress or occupancy.
Install of temp Platform, Sculpture, no alt to exist structures for Vertical Highways. A TPA not required. Producer is responsible to monitor site safety & implement HWAP. All prod…
Sidewalk shed installation as shown on drawings. no change in use, egress or occupancy. we shall comply with chapter 33 of 2022 b.c
Alteration type 3 - construction equipment - sidewalk- shed proposed installation of heavy duty sidewalk shed. no change in use occupancy or egress under this application. live loa…
Demolition and Construction of Air Conditioning Ductwork, Supply Air Diffusers & Grilles and Return Air Grilles on Part of the 17th Floor
Renovation of existing office spaces on the 8th floor as per drawings filed herewith. no change to use, occupancy, or egress
Plumbing work at cellar and 1st floor beauty salon of an existing 14-story building. related general construction work has been filed initially. no change in use, egress or certifi…
Installation of single cage 7000# capacity personnel/material hoist hoist shall comply with ch #33 of the nyc bc. no change in use, occupancy or egress under this application. elev…
Temporary hoist run-back structure during bldg alt, filed separately. hoist run-back structure shall comply with chapter #33 of the nyc building code. no change in use, occupancy o…
Installation of temporary construction fence and sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy…
Erect illuminated accessory businessd/f blade sign-b @west 48th st elevation as per drawing file herewith
Structural changes as indicated on plans; including framing for new partition wall door.
Early-phase Mechanical modifications to fan powered boxes and fans on Floors 27 through 29. Construction costs and filing fees included in full-floor Mechanical job # M01293931-S1.…
General construction modifications taking place on the 21st floor as per plans filed herewith. No change in use, egress or occupancy
Minor demolition with installation of new partitions on the 28th floor as per plans. No change to Use, Egress or Occupancy.
Structural modifications on MZ1 as per plans filed herewith. No changes in use, egress or occupancy.
Sprinkler/Plumbing modifications as per plans filed herewith. No change to use, egress or occupancy.
Structural modifications taking place on the 16th fl Construction/ 17th fl Marketing floor as per plans filed herewith. No change in use, egress or occupancy